41 weeks of schedule recovered on a 30 MW colocation campus

Southeast US - MV and LV switchgear package - identifying details withheld under NDA.

74 wksIncumbent quote
19 wksSwitchpoint delivery
41 wksSchedule recovered vs plan
12 + 8MV sections + LV boards

The situation

A 30 MW colocation expansion had energization committed to an anchor tenant. The specified switchgear manufacturer returned a 74-week delivery on the MV lineup - putting gear arrival 10 months after the committed energization date. The EOR, contractor, and owner needed an approved-equal alternate that could survive engineering review, not just a promise.

What happened

  • Week 0: One-line and fault study received; budget pricing and written 19-week delivery returned in two business days.
  • Week 2: Submittal package through EOR review; approved-equal listing granted. Production slot reserved ahead of the formal award.
  • Week 5: Released to production. Weekly reports with photos to the owner and contractor from that point forward.
  • Week 21: Factory witness test with the commissioning agent; shipped same week.
  • Week 24: Energized. 41 weeks ahead of where the incumbent quote would have landed the project.

Representative project profile. Counterparty details withheld; figures rounded to protect confidentiality.

UL 1558
UL 891
ANSI C37.20.2
IEEE C37
NEMA
IBC seismic

Carrying a date you cannot currently make?

Send the one-line. If we can recover your schedule, you will know this week.

Price a live project
Switchpoint 2026Nashville, TNHomeProductsPartnersRequest a quoteTeam sign in