Home / Lead times / Magnum DS switchgear (UL 1558)

Magnum DS switchgear (UL 1558)

Updated 2026-09-04 · Low-voltage switchgear (UL 1558, draw-out) · by Switchpoint, Nashville and Charlotte

Magnum DS switchgear (UL 1558): OEM factory lead time is quoting 54-84 weeks as of 2026-08 across 3 dated sources. Switchpoint: bring it, we will look.

WhatWeeksAs ofSource
480V draw-out54 weeks2026-08VAWN Electrical Equipment Lead Time Index - LV switchgear about 54 weeks
LV draw-out switchgear70-80 weeks2026-06Barton Associates via Metapress - LV draw-out switchgear 70 to 80 weeks; ATS 45 to 80
power circuit breaker switchboards84 weeks2026-03Electronate - Power circuit breaker switchboards pushing past 84 weeks
Switchpoint assembled through certified UL panel shops or direct shipbring it, we will look2026-09Quoted case by case; send the RFQ
Trend, oldest to newest: 2026-03: 84 weeks → 2026-06: 70-80 weeks → 2026-08: 54 weeks

Get a Switchpoint number for this gear Back to the board

Report a quote

Got a real number from a manufacturer or distributor? Add it. We anonymize it and it moves the board. This is how the board stays honest.

Got a quote in hand?

Send us the RFQ and get a Switchpoint number inside a week, or report the quote and move the board.