As of September 2026, low-voltage switchboards are quoting 32-62 weeks from OEM factories and medium-voltage metal-clad switchgear 40-156 weeks, based on dated industry sources listed on each page. Switchpoint delivers assembled UL 891 switchboards in 6-10 weeks through certified panel shops (verification of each menu row in progress).
| Product family | Maker | Factory, this month | As of | Switchpoint |
|---|---|---|---|---|
| Pow-R-Line switchboards | Eaton | 32-62 weeks | 2026-08 | 6-10 weeks, assembled (UL 891) |
| QED-6 switchboards | Schneider (Square D) | 32-62 weeks | 2026-08 | 6-10 weeks, assembled (UL 891) |
| Magnum DS switchgear (UL 1558) | Eaton | 54-84 weeks | 2026-08 | bring it, we will look |
| MNS low-voltage switchgear | ABB | 54-84 weeks | 2026-08 | bring it, we will look |
| Model 6 motor control centers | Schneider (Square D) | 30-55 weeks | 2024-04 | verified on request |
| Freedom 2100 motor control centers | Eaton | 30-55 weeks | 2024-04 | verified on request |
| VacClad-W metal-clad switchgear | Eaton | 40-156 weeks | 2026-07 | case by case; under 52 weeks is the ask |
| GM-SG metal-clad switchgear | Siemens | 40-156 weeks | 2026-07 | case by case; under 52 weeks is the ask |
| MV metal-clad switchgear, 5-15 kV | All makers | 40-156 weeks | 2026-07 | case by case; under 52 weeks is the ask |
| Pad-mount distribution transformers | All makers | 40-130 weeks | 2026-06 | direct ship, ask |
Type a question about lead times. Answers come only from verified rows on this board, with citations. No account required.
Each row is the range across dated public sources from the last nine months: manufacturer-published lead-time adjustments, supply-chain surveys, earnings calls, and trade reporting, plus quotes reported to Switchpoint through the RFQ desk (anonymized). Older sources stay on the page, marked with their date, so the trend is visible. The Switchpoint column is our delivery path for the same gear. Rows marked "verification in progress" are our supply partner's program figures being confirmed line by line. Report a quote on any page to move the lead times.
Send an RFQ Suppliers: commit weeks
Verified lead-time rows are available as a Model Context Protocol endpoint at https://mcp.switchpointgear.com/public. No authentication required. One tool: lead_times(family?, maker?). Returns the same verified rows shown on this board, with source citations.
POST https://mcp.switchpointgear.com/public{"jsonrpc":"2.0","id":1,"method":"tools/list"}{"jsonrpc":"2.0","id":2,"method":"tools/call","params":{"name":"lead_times","arguments":{"maker":"Eaton"}}}family, maker, rating, weeks_low, weeks_high, as_of, source, source_url
Send us the RFQ and get a Switchpoint number in one to two weeks, or report the quote and move the lead times.