Home / Lead times / QED-6 switchboards

QED-6 switchboards

Updated 2026-09-04 · Low-voltage switchboards (UL 891) · by Switchpoint, Nashville and Charlotte

QED-6 switchboards: OEM factory lead time is quoting 32-62 weeks as of 2026-08 across 3 dated sources. Switchpoint: 6-10 weeks, assembled (UL 891). The Switchpoint figure is from our supply partner's program materials and is being verified line by line; verified rows say so.

WhatWeeksAs ofSource
480V, up to 4000A32-41 weeks2026-08VAWN Electrical Equipment Lead Time Index (aggregates Siemens CompAS lead-time adjustments) - Switchboards 32 to 41 weeks
large LV switchboards35-62 weeks2026-06DEI Power, Electrical Switchgear Shortage - Large LV switchboards 35 to 62 weeks vs 20 to 30 pre-pandemic
standard switchboards52 weeks2026-03Electronate, Switchgear Lead Times in 2026 - Standard switchboards 52 weeks; power circuit breaker switchboards past 84
MV and LV Square D Schneider (Square D)30-65 weeks2024-04Electrician Talk thread (contractor report) - Square D MV and LV 30 to 65 weeks; older report
Switchpoint assembled through certified UL panel shops or direct ship6-10 weeks, assembled (UL 891)2026-09PSG program materials; verification in progress
Trend, oldest to newest: 2026-03: 52 weeks → 2026-06: 35-62 weeks → 2026-08: 32-41 weeks

Capacity and demand notes

Get a Switchpoint number for this gear Back to the board

Report a quote

Got a real number from a manufacturer or distributor? Add it. We anonymize it and it moves the board. This is how the board stays honest.

Got a quote in hand?

Send us the RFQ and get a Switchpoint number inside a week, or report the quote and move the board.