Home / Lead times / MV metal-clad switchgear, 5-15 kV

MV metal-clad switchgear, 5-15 kV

Updated 2026-09-04 · Medium-voltage metal-clad switchgear · by Switchpoint, Nashville and Charlotte

MV metal-clad switchgear, 5-15 kV: OEM factory lead time is quoting 40-156 weeks as of 2026-07 across 3 dated sources. Switchpoint: case by case; under 52 weeks is the ask.

WhatWeeksAs ofSource
MV, many channels104-156 weeks2026-07Trade coverage (Build Inc., Data Center Knowledge) via getuniqcli - MV switchgear described as effectively sold out through 2028 in many channels
standard MV52-80 weeks2026-06Terrapin Consulting Group (2026 slot reservations) - Standard MV switchgear 52 to 80 weeks by manufacturer, voltage class, quantity
MV40-80 weeks2026-06DEI Power - MV switchgear 40 to 80 weeks, more than double pre-pandemic
5 to 15 kV44 weeks2025-06Wood Mackenzie T&D supply-chain survey (Q2 2025) via VAWN - Switchgear about 44 weeks (Q2 2025 figure)
Switchpoint assembled through certified UL panel shops or direct shipcase by case; under 52 weeks is the ask2026-09Quoted case by case; send the RFQ
Trend, oldest to newest: 2026-06: 40-80 weeks → 2026-06: 52-80 weeks → 2026-07: 104-156 weeks

Capacity and demand notes

Get a Switchpoint number for this gear Back to the board

Report a quote

Got a real number from a manufacturer or distributor? Add it. We anonymize it and it moves the board. This is how the board stays honest.

Got a quote in hand?

Send us the RFQ and get a Switchpoint number inside a week, or report the quote and move the board.

Send an RFQ
SWGR LLC dba Switchpoint Gear ยท 2026Nashville, TNHomeProductsPartnersRequest a quote