VacClad-W metal-clad switchgear: OEM factory lead time is quoting 40-156 weeks as of 2026-07 across 3 dated sources. Switchpoint: case by case; under 52 weeks is the ask.
| What | Weeks | As of | Source |
|---|---|---|---|
| MV, many channels | 104-156 weeks | 2026-07 | Trade coverage (Build Inc., Data Center Knowledge) via getuniqcli - MV switchgear described as effectively sold out through 2028 in many channels |
| standard MV | 52-80 weeks | 2026-06 | Terrapin Consulting Group (2026 slot reservations) - Standard MV switchgear 52 to 80 weeks by manufacturer, voltage class, quantity |
| MV | 40-80 weeks | 2026-06 | DEI Power - MV switchgear 40 to 80 weeks, more than double pre-pandemic |
| 5 to 15 kV | 44 weeks | 2025-06 | Wood Mackenzie T&D supply-chain survey (Q2 2025) via VAWN - Switchgear about 44 weeks (Q2 2025 figure) |
| Switchpoint assembled through certified UL panel shops or direct ship | case by case; under 52 weeks is the ask | 2026-09 | Quoted case by case; send the RFQ |
Get a Switchpoint number for this gear Back to the board
Got a real number from a manufacturer or distributor? Add it. We anonymize it and it moves the board. This is how the board stays honest.
Send us the RFQ and get a Switchpoint number inside a week, or report the quote and move the board.