Model 6 motor control centers: OEM factory lead time is quoting 30-55 weeks as of 2024-04 across 1 dated sources. Switchpoint: verified on request. The Switchpoint figure is from our supply partner's program materials and is being verified line by line; verified rows say so.
| What | Weeks | As of | Source |
|---|---|---|---|
| LV MCC Schneider (Square D) | 30-55 weeks | 2024-04 | Electrician Talk thread (contractor report) - LV MCCs 30 to 55 weeks; older report, verify at quote |
| Switchpoint assembled through certified UL panel shops or direct ship | verified on request | 2026-09 | PSG program materials; verification in progress |