Pad-mount distribution transformers: OEM factory lead time is quoting 40-130 weeks as of 2026-06 across 2 dated sources. Switchpoint: direct ship, ask.
| What | Weeks | As of | Source |
|---|---|---|---|
| pad-mount service | 110-130 weeks | 2026-06 | Barton Associates via Metapress - Pad-mount service transformers 110 to 130 weeks |
| up to 5 MVA | 40-65 weeks | 2026-06 | Terrapin Consulting Group - Pad-mount distribution transformers 40 to 65 weeks |
| Switchpoint assembled through certified UL panel shops or direct ship | direct ship, ask | 2026-09 | Quoted case by case; send the RFQ |